When the system contains air and the filters and input pipe work are not completely full of fuel, the filters will need to be bled of air and system primed. The system does not automatically purge air, so it is the engineer’s responsibility to do so as described in later sections.
The Grey Filter should be topped up with fuel to the brim.
The Blue Filter should be topped up with fuel to cover the Output pipe.
Ensure the entire input pipe work is full of fuel and there are no air pockets.
If possible, a simple way to achieve the above priming procedure during machine installation is to connect the input pipe to the tank, but leave the output pipe work disconnected. Use a manual or electronic priming pump to pull a vacuum on the output of the system, and assuming the only ball valve open is the isolating one on the input side of the system, this should draw fuel from the tank, through the input pipe work and into the system. When fuel starts to emerge from the priming pump, switch it off and close all ball valves. The unit is now fully primed and the output pipe work can be attached.
If a priming tee has been installed at the highest point then an alternative priming method is to close the output isolating ball valve, and leave the input isolating ball valve open.
Now pour fuel into the priming tee. With the correct setup, this should start to fill the system with fuel. Open the air-bleed valve on the top of the blue coalescing filter, when fuel emerges, close it again, but keep filling up at the priming tee until all the air has been removed.
Regardless of the method chosen, we recommend:
NOTE; A loud noise from within the system, or a rapid increase in temperature at the pump head are indications of a lack of fuel flow. In either case, please stop the system immediately to avoid damage, and repeat the priming procedure.
If you have the optional flow sensor attached, the system will tell you. If you do not have the optional sensor, please refer to the “User area and password system” section of this manual to found out how to setup the system to achieve basic fuel flow sensing system.
CAUTION: The discharge isolating valve must be opened immediately after starting the system. Otherwise the pump head may be damaged.
NOTE: If it is difficult for the pump to build up pressure, it may be necessary to repeat steps 1 to 10.
Environmental note
If your system is to be installed and operated in corrosive environments, for example near to the coast, or in extreme weather conditions, we recommend regular checking and treatment of all metal parts. Although stainless steel and treated steel have been used in the constriction of your system, water and corrosive elements can case contamination which may in some circumstances damage the surface oct her system.
To avoid this, we recommend regular periodic inspection of the system, for example a monthly check; although the frequency may need to be altered depending on the environment experienced. We also recommend protecting all metal surfaces with a suitable degreaser or water repellent protective oil such as WD40 or NanoShell metal, regular repeated treatment may be required to maintain the prising condition your unit was supplied in.
WASP PFS have created the ideal solution for easy automatic or manual priming. These priming units can be used as an add-on to the W-PFS or WB Fuel Polishing Range or as a stand alone priming solution.
Use this form to get a competitive quote!
Check out our interactive WASP Fuel Polishing System
Try our interactive product selector